Roundabout proposed near Moreland


  • By The Newnan Times-Herald
  • |
  • Nov. 20, 2020 - 2:29 PM

Donate To Support Local Journalism.

Please consider making a donation so we can continue to bring you the latest news and information on COVID-19 in our community.

Donate Now
Roundabout proposed near Moreland

GDOT

The Georgia Department of Transportation (Georgia DOT) has approved the location and design for a project that would install a five-leg single-lane roundabout at the current intersection of US 29/Georgia 14 at US 27 ALT/Georgia 41 just outside Moreland.

The Georgia Department of Transportation has approved the location and design for a project that would install a five-leg, single-lane roundabout at the current intersection of US 29/Georgia 14 at US 27 ALT/Georgia 41 just outside Moreland.

The design and location were approved on Oct. 8, 2020.

The project will convert the intersection into a roundabout and also install pedestrian crosswalks and ADA ramps. It begins approximately 900 feet south of the US 29/Georgia 14 and US 27 ALT/Georgia 41 intersection and ends approximately 700 feet north of that intersection.

The project is located at the southern border of the city of Moreland in Coweta County in Land Lots 165 and 166 of Land District 2.

The project has an approximate construction schedule of 18 months. During construction, staging will be utilized to build the roundabout under traffic, so that the roadways can remain open. Temporary pavement, traffic shifts and occasional lane closures will be installed.

Due to current COVID-19 measures, those who wish to view the drawings or plats in person must make an appointment in advance. Anyone wishing to make an appointment, or to ask questions or voice concerns about the project, should call 706-845-4115 or email Area Engineer William Boyd for the District 3/Area 5 office: wboyd@dot.ga.gov .